EDF Energy has insisted it is making ‘good progress’ on appointing a preferred bidder at Hinkley Point C, just a week after one of the bidders told CN the contract is unlikely to be awarded before 2013.
A spokesman said the energy firm expects to be able to “make an announcement to take forward this particular contract soon” despite repeated delays in the scheme which industry experts had expected to go to preferred bidder status before now.
The Control of Asbestos Regulations 2012 came into force on 6 April 2012, updating previous asbestos regulations to take account of the European Commission's view that the UK had not fully implemented the EU Directive on exposure to asbestos (Directive 2009/148/EC).
In practice the changes are fairly limited. They mean that some types of non-licensed work with asbestos now have additional requirements, i.e. notification of work, medical surveillance and record keeping. All other requirements remain unchanged.
What has stayed the same?
© Copyright 2013 Qube Solution Services Ltd. | Site Map